Our company found the following problems during the inspection of "big, fast and strict" potential safety hazards on April 25, 2016, and now publicize them to the public as follows:
1. The second layer tool box shall be painted and cleaned
2.5# tower kettle liquid tank ladder damaged
3. The pipeline direction and material name are not standardized
4. The site sampling port is dirty and disorderly
The Department has been ordered to complete the rectification of the above departments before May 20, 2016, meet the requirements of relevant laws, regulations and standards, take safety precautions during the rectification period, and eliminate the occurrence of safety accidents!
Monthly safety inspection of "big, fast and strict"